Technologies Successfully Implemented |
|
September 2015 |
Steel Pipe Support Design for
Water Mains |
The original structural
concept of the water main under the bridge (that
was provided in tender documents) had some fatal
flaws. After presenting concerns to the owner
and their consulting team, PROF&E's engineers
developed a solution that reduced construction
cost, reduced reactions on the existing bridge
and controlled movement of the main within 25
mm. The proposed solution was implemented
this summer and the main successfully passed
pressure test this September. |
|
|
|
August 2015 |
(NEW) Steel Thrust Supports
for High-Pressure Mains |
Concrete thrust blocks in
valve chambers, pumping stations and water /
wastewater plants could be a history. Our
patented steel thrust supports are much easier
to install, less expensive, they require less
real estate, and they could be removed if
needed. Call us and we will provide you with
all necessary details for your project. |
|
|
|
October 2014 |
Low Pressure Injection Repairs using Epoxy
Resin |
After conclusive evidence by
TTC that the topping slab has not bonded to the
substrate concrete in all areas as specified,
PROF&E engineers were engaged to examine field
conditions and develop a solution that will
eliminate a need for complete demolition of
topping slab at TTC Spadina Station, Streetcar
Platform. The
structural repair work was successfully completed in less
than 5 months, including approvals by TTC. It
involved low-pressure epoxy injection that
"stitched" topping together with the base
concrete slab, The ultimate product exceeded
specified bond criteria. |
|
|
|